June 7,
It looks like these tanks are just going to take awhile to make. I might as well settle into the task and let it take how long it will take.
![]() |
This blackwater tank is getting complicated. All of the interior baffles and inspection port reinforcement are in place. |
![]() |
Just another view showing how the internal flow will occur. The baffles are placed to support the sides and inspection port. |
For the hose attachments, I plan on using short pieces HDPE pipe that I can weld on. I'll make the barbs with the lathe. The 1 1/2" pump-out will be an internal pipe that siphons from the deepest part of the tank.
June 12,
![]() |
The second black water tank being built. |
![]() |
Remember this step from above. This is the port tank and the inspection port will be centered (more or less) on the tank and accessible from under the galley sink. |
No comments:
Post a Comment
Your feedback is very much appreciated.